Shoddy handling of irrigation project in Plateau community upsets verification team

371
0

A project verification team from the Fiscal Responsibility Commission has expressed dissatisfaction over the handling of the N734 million Barkin-Ladi Irrigation Scheme project in Plateau.

The Team Leader, Sampson Eletuo, who spoke after inspecting work done on the project, declared that project execution was “less than 60 per cent”.

“The Project Engineer, Garba Bello, a staff of the Federal Ministry of Water Resources, has said that 95 per cent of the job has been completed.

“He has also told us that the project will be inaugurated in December, which is just next month.

“But,from what is on ground, not much has been executed, there is no way the project can be inaugurated this year because both the irrigation and dam components are not ready,” Eletuo said.

He said that the work appeared to have been abandoned because the handlers were not at the site, while the contractor was not around to answer questions raised by the verification team.

“The verification team is particularly disappointed that the contractor was not physically present to confirm how much he has so far collected; that would have helped us to assess what is on ground,” he said.

Reacting, Bello said that the opinion of the verification team was not a true reflection of work already carried out at the project site.

“I think the team’s assessment is based on the dam component of the project, which is 25 per cent completed.

“I have taken them round the irrigation component and they have seen that it is more than 90 per cent completed,” he said.

He rejected suggestions that he had shielded the handlers from the team, saying that workers of the construction firm represented the principal handler who had traveled out of the country.

Bello said that “about N440 million” had so far been paid to the contractor, adding, however, that work so far done had exceeded that amount “by far”.

Bello informed the team, during the inspection, that a 5,000 KVA power generating plant was already at the site, while nozzles to be used to pipe water for dry season farming had been installed.

According to him, the irrigation scheme will ease dry season farming, boost the production of Irish potatoes and assorted fruits, and also create jobs.

The project was awarded in 2014 by former Minister of Water Resources, Sarah Ochekpe, who hails from Barkin-Ladi.